October 9, 2021

Standby Contract Agreement

Filed under: Uncategorized — dpk3000 @ 12:46 am

The board concluded that the contractor did not have to bear any overhead costs as a result of the suspension, as the incumbent had no staff or equipment on site during the suspension and could also take over five other contracts. Where a contractor retains equipment and personnel on the same site, as the contractor has done, and has not been able to resume further work because the equipment has been kept on hold, restoration is permitted. Z.B.M.E. Brown, a.o.a. To cover the “watch” costs, the contractor must first prove that he had to stand next to him and that the delay affected his operation in such a way that it was not possible to carry out other work. Gregory Constructors, Inc., 88-3 BCA 20,934 (ASBCA, May 31, 1988), based on Capital Electric Company v. United States, 729 F.2d 743 (Fed. Cir. 1984). The suspension clause also provides that the government`s suspension order must be made in writing.